Brick Calculator – Bricks, Cement and Sand for a Wall

Enter wall length, height and thickness, deduct doors and windows, and pick the brick size and mortar mix. You get bricks (with breakage), mortar, cement bags and sand.

Units
ft
ft
Thickness
sqft
%

Result

Preliminary estimate
Bricks
999
incl. breakage (952 net)
Cement
2.9 bags
CM 1:6
Sand
21.1 cft
0.6 m³
Volume
2.33 m³
net brickwork

Step-by-step working

  1. 1
    Wall volume
    3.962 × 3.048 × 0.23
    2.778 m³
  2. 2
    Less openings
    1.95 m² × 0.23
    −0.449 m³
  3. 3
    Net brickwork
    2.329 m³
  4. 4
    One brick with mortar
    (0.23+0.01) × (0.11+0.01) × (0.075+0.01)
    0.002448 m³
  5. 5
    Number of bricks
    2.329 ÷ 0.002448
    952 nos
  6. 6
    With breakage
    952 × (1 + 5%)
    999 nos
  7. 7
    Wet mortar
    2.329 − 951.4 × 0.001898
    0.524 m³
  8. 8
    Dry mortar
    0.524 × 1.33
    0.697 m³
  9. 9
    Cement (1:6)
    0.697 ÷ 7 ÷ 0.0347
    2.87 bags
  10. 10
    Sand
    0.697 × 6 / 7
    0.597 m³ = 21.1 cft

Assumptions

  • Brick: Traditional 230 × 110 × 75 mm, mortar joint 10 mm.
  • Mortar dry volume factor 1.33 (includes frog filling and bulking).
  • Brick breakage 5%.
  • Openings deducted in full (IS 1200: openings up to 0.1 m² are not deducted).

Frequently asked questions

How many bricks are in 1 m³ of brickwork?

About 500 modular bricks (190 × 90 × 90 mm) with 10 mm joints, before breakage.

How much cement is needed for 1 m³ of brickwork in 1:6?

About 1.26 bags of cement and 0.26 m³ of sand, using a dry mortar factor of 1.33.

Should openings be deducted?

Yes. As per IS 1200, openings larger than 0.1 m² are deducted from brickwork.