Enter the size of the slab, beam, column or footing and choose the mix. The calculator applies the 1.54 dry volume factor and shows cement bags, sand and aggregate in m³ and cft.

Units
ft
ft
ft
nos
%

Result

Preliminary estimate
Cement
12.4 bags
621 kg
Sand
22.8 cft
0.65 m³
Aggregate
45.7 cft
1.29 m³
Volume
1.509 m³
53.3 cft

Step-by-step working

  1. 1
    Wet volume of concrete
    1.509 m³
  2. 2
    Dry volume (with wastage)
    1.509 × 1.54 × (1 + 2%)
    2.371 m³
  3. 3
    Mix M20
    1 : 1.5 : 3 → total parts
    5.5
  4. 4
    Cement volume
    2.371 × 1 / 5.5
    0.431 m³
  5. 5
    Cement bags
    0.431 ÷ 0.0347 m³ per bag
    12.41 bags
  6. 6
    Sand
    2.371 × 1.5 / 5.5
    0.647 m³ = 22.8 cft
  7. 7
    Aggregate
    2.371 × 3 / 5.5
    1.293 m³ = 45.7 cft

Assumptions

  • Nominal mix M20 (1:1.5:3); for design mixes use the mix design proportions.
  • Dry volume factor 1.54 (voids + shrinkage).
  • Cement bag 50 kg = 0.0347 m³ (density 1440 kg/m³).
  • Wastage 2%.

Frequently asked questions

How many cement bags are needed for 1 m³ of M20 concrete?

About 8.06 bags for nominal mix M20 (1:1.5:3): dry volume 1.54 m³ × 1/5.5 = 0.28 m³ of cement ÷ 0.0347 m³ per bag.

Why multiply by 1.54?

Dry materials shrink when water is added and voids fill up. 1.54 converts wet concrete volume to the dry volume of materials.

What mix is used for PCC and for RCC?

PCC below footings and floors is usually M7.5 (1:4:8) or M10 (1:3:6). RCC slabs, beams and columns in houses are usually M20 or higher, as per the structural design.