House Construction Cost Calculator
Enter the built-up area, floors, location and quality. You get the total cost, cost per sqft, material quantities by thumb rule, cost by construction stage and a suggested payment schedule.
Start with your built-up area
Enter the area you will build on each floor, rather than the full plot area. Example: 1,000 sq ft per floor with G+1 means 2,000 sq ft in total. The starting numbers are examples; results update as you edit.
G = ground floor only · G+1 = ground + first floor
- per sqft
- ₹1,700
- Built-up
- 2,000 sqft
- Approx. construction time
- ~10 months
Likely range (±10%): ₹30,60,000 – ₹37,40,000
Materials needed
Change any rate to see your own cost.
- MaterialThumb rule / sqftQuantityRate (₹)Amount
- Cement0.4 bags/sqft0.4 bags800 bags₹3,04,000
- Steel4 kg/sqft4 kg8,000 kg₹5,20,000
- Sand1.816 cft/sqft1.816 cft3,632 cft₹2,17,920
- Aggregate1.35 cft/sqft1.35 cft2,700 cft₹1,35,000
- Bricks8 nos/sqft8 nos16,000 nos₹1,28,000
- Tiles1.3 sqft/sqft1.3 sqft2,600 sqft₹1,43,000
- Paint0.18 litre/sqft0.18 litre360 litre₹90,000
Cost by stage
- Site preparation & excavation₹1,02,000
- Foundation & plinth₹4,08,000
- RCC structure (columns, beams, slabs)₹8,50,000
- Brickwork₹3,40,000
- Plastering₹2,04,000
- Flooring & tiling₹2,72,000
- Doors & windows₹2,72,000
- Electrical₹2,04,000
- Plumbing & sanitary₹2,38,000
- Painting₹1,70,000
- Waterproofing₹68,000
- Staircase, parapet & misc.₹1,02,000
- Contingency₹1,70,000
Cost split
- Materials · 60%₹20,40,000
- Labour · 30%₹10,20,000
- Equipment, transport & misc. · 5%₹1,70,000
- Contingency · 5%₹1,70,000
Suggested payment schedule
| Milestone | Share | Amount |
|---|---|---|
| On agreement / booking | 10% | ₹3,40,000 |
| Foundation complete | 15% | ₹5,10,000 |
| Plinth complete | 10% | ₹3,40,000 |
| Ground floor – slab cast | 15% | ₹5,10,000 |
| 1st floor – slab cast | 15% | ₹5,10,000 |
| Brickwork | 10% | ₹3,40,000 |
| Plaster & flooring complete | 15% | ₹5,10,000 |
| Finishing & handover | 10% | ₹3,40,000 |
Step-by-step working
- 1Built-up area1000 sqft × 2 floor(s)2000 sqft
- 2Rate per sqft₹1,700 (standard) × 1 (location)₹1,700/sqft
- 3Total cost2000 × ₹1,700₹34,00,000
- 4Cement2000 × 0.4 bags/sqft800 bags
- 5Steel2000 × 4 kg/sqft8000 kg
- 6Sand2000 × 1.816 cft/sqft3632 cft
- 7Aggregate2000 × 1.35 cft/sqft2700 cft
- 8Bricks2000 × 8 nos/sqft16000 nos
Assumptions
- Thumb-rule (area based) estimate for an RCC framed house; ±10% accuracy.
- Base rate ₹1,700/sqft for standard quality, location factor 1.
- Includes structure, masonry, plaster, flooring, doors/windows, electrical, plumbing, painting, waterproofing.
- Excludes land, approvals, interiors, furniture, compound wall, borewell, water tank.
- For a detailed BOQ with measurement book, use the plan-based Detailed Estimate.
Frequently asked questions
What is the construction cost per sqft in India in 2026?
For an RCC framed house it is roughly ₹1,400–1,550 per sqft for basic quality, ₹1,600–1,800 for standard and ₹2,300+ for premium in a tier-2 city, higher in metros. A single-storey house costs about 8–10% more per sqft than G+1 because the foundation and roof are shared by less area. Use the rate box to enter your local rate.
How much cement and steel does a 1000 sqft house need?
By thumb rule about 400 bags of cement (0.4 bag/sqft) and 3.5–4.5 tonnes of steel (about 4 kg/sqft) for 1000 sqft of built-up area.
How accurate is this estimate?
It is an area-based estimate, usually within ±10%. For an item-wise BOQ with measurement book you need the plan, which is what the Detailed Estimate does.
What is not included?
Land, approvals and fees, interiors, furniture, modular kitchen, compound wall, borewell and water tank are not included.