GGuniyo

House Construction Cost Calculator

Enter the built-up area, floors, location and quality. You get the total cost, cost per sqft, material quantities by thumb rule, cost by construction stage and a suggested payment schedule.

Start with your built-up area

Enter the area you will build on each floor, rather than the full plot area. Example: 1,000 sq ft per floor with G+1 means 2,000 sq ft in total. The starting numbers are examples; results update as you edit.

sqft

G = ground floor only · G+1 = ground + first floor

Floors
Quality
₹
Enter your local rate if you know it
Total estimated costPreliminary estimate
₹34,00,000
≈ ₹34 lakh
per sqft
₹1,700
Built-up
2,000 sqft
Approx. construction time
~10 months

Likely range (±10%): ₹30,60,000 – ₹37,40,000

Materials needed

Change any rate to see your own cost.

  • Cement0.4 bags/sqft800 bags₹3,04,000
  • Steel4 kg/sqft8,000 kg₹5,20,000
  • Sand1.816 cft/sqft3,632 cft₹2,17,920
  • Aggregate1.35 cft/sqft2,700 cft₹1,35,000
  • Bricks8 nos/sqft16,000 nos₹1,28,000
  • Tiles1.3 sqft/sqft2,600 sqft₹1,43,000
  • Paint0.18 litre/sqft360 litre₹90,000

Cost by stage

  • Site preparation & excavation₹1,02,000
  • Foundation & plinth₹4,08,000
  • RCC structure (columns, beams, slabs)₹8,50,000
  • Brickwork₹3,40,000
  • Plastering₹2,04,000
  • Flooring & tiling₹2,72,000
  • Doors & windows₹2,72,000
  • Electrical₹2,04,000
  • Plumbing & sanitary₹2,38,000
  • Painting₹1,70,000
  • Waterproofing₹68,000
  • Staircase, parapet & misc.₹1,02,000
  • Contingency₹1,70,000

Cost split

  • Materials · 60%₹20,40,000
  • Labour · 30%₹10,20,000
  • Equipment, transport & misc. · 5%₹1,70,000
  • Contingency · 5%₹1,70,000

Suggested payment schedule

MilestoneShareAmount
On agreement / booking10%₹3,40,000
Foundation complete15%₹5,10,000
Plinth complete10%₹3,40,000
Ground floor – slab cast15%₹5,10,000
1st floor – slab cast15%₹5,10,000
Brickwork10%₹3,40,000
Plaster & flooring complete15%₹5,10,000
Finishing & handover10%₹3,40,000

Step-by-step working

  1. 1
    Built-up area
    1000 sqft × 2 floor(s)
    2000 sqft
  2. 2
    Rate per sqft
    ₹1,700 (standard) × 1 (location)
    ₹1,700/sqft
  3. 3
    Total cost
    2000 × ₹1,700
    ₹34,00,000
  4. 4
    Cement
    2000 × 0.4 bags/sqft
    800 bags
  5. 5
    Steel
    2000 × 4 kg/sqft
    8000 kg
  6. 6
    Sand
    2000 × 1.816 cft/sqft
    3632 cft
  7. 7
    Aggregate
    2000 × 1.35 cft/sqft
    2700 cft
  8. 8
    Bricks
    2000 × 8 nos/sqft
    16000 nos

Assumptions

  • Thumb-rule (area based) estimate for an RCC framed house; ±10% accuracy.
  • Base rate ₹1,700/sqft for standard quality, location factor 1.
  • Includes structure, masonry, plaster, flooring, doors/windows, electrical, plumbing, painting, waterproofing.
  • Excludes land, approvals, interiors, furniture, compound wall, borewell, water tank.
  • For a detailed BOQ with measurement book, use the plan-based Detailed Estimate.
Need an item-wise BOQ with measurement book, BBS and a drawn plan? Use the Item-wise House BOQ →

Frequently asked questions

What is the construction cost per sqft in India in 2026?

For an RCC framed house it is roughly ₹1,400–1,550 per sqft for basic quality, ₹1,600–1,800 for standard and ₹2,300+ for premium in a tier-2 city, higher in metros. A single-storey house costs about 8–10% more per sqft than G+1 because the foundation and roof are shared by less area. Use the rate box to enter your local rate.

How much cement and steel does a 1000 sqft house need?

By thumb rule about 400 bags of cement (0.4 bag/sqft) and 3.5–4.5 tonnes of steel (about 4 kg/sqft) for 1000 sqft of built-up area.

How accurate is this estimate?

It is an area-based estimate, usually within ±10%. For an item-wise BOQ with measurement book you need the plan, which is what the Detailed Estimate does.

What is not included?

Land, approvals and fees, interiors, furniture, modular kitchen, compound wall, borewell and water tank are not included.