Building 800 sq ft of built-up area costs about ₹13.6 lakh at standard finish — ₹1,700 per sq ft, material and labour together, in a tier-2 city in 2026. Below: cost by finish level, the material you will buy, what each stage costs, and a calculator to change area, floors and city.

Standard cost
₹13.6 lakh
Rate
₹1,700/sq ft
Cement
320 bags
Steel
3.2 tonnes

Cost by finish level

FinishRate per sq ftTotalRange ±10%
Basic₹1,450₹11.6 lakh₹10.4 lakh – ₹12.8 lakh
Standard₹1,700₹13.6 lakh₹12.2 lakh – ₹15.0 lakh
Premium₹2,400₹19.2 lakh₹17.3 lakh – ₹21.1 lakh

Material for a 800 sq ft house

MaterialPer sq ftQuantityApprox. cost
Cement0.4 bags320 bags₹1,21,600
Steel4 kg3,200 kg₹2,08,000
Sand1.816 cft1,453 cft₹87,168
Aggregate1.35 cft1,080 cft₹54,000
Bricks8 nos6,400 nos₹51,200
Tiles1.3 sqft1,040 sqft₹57,200
Paint0.18 litre144 litre₹36,000

Stage-wise cost

StageShareAmount
Site preparation & excavation3%₹40,800
Foundation & plinth12%₹1,63,200
RCC structure (columns, beams, slabs)25%₹3,40,000
Brickwork10%₹1,36,000
Plastering6%₹81,600
Flooring & tiling8%₹1,08,800
Doors & windows8%₹1,08,800
Electrical6%₹81,600
Plumbing & sanitary7%₹95,200
Painting5%₹68,000
Waterproofing2%₹27,200
Staircase, parapet & misc.3%₹40,800
Contingency5%₹68,000

Change area, floors, finish or city

Start with your built-up area

Enter the area you will build on each floor, rather than the full plot area. Example: 1,000 sq ft per floor with G+1 means 2,000 sq ft in total. The starting numbers are examples; results update as you edit.

sqft

G = ground floor only · G+1 = ground + first floor

Floors
Quality
₹
Enter your local rate if you know it
Total estimated costPreliminary estimate
₹13,60,000
≈ ₹13.6 lakh
per sqft
₹1,700
Built-up
800 sqft
Approx. construction time
~7 months

Likely range (±10%): ₹12,24,000 – ₹14,96,000

Materials needed

Change any rate to see your own cost.

  • Cement0.4 bags/sqft320 bags₹1,21,600
  • Steel4 kg/sqft3,200 kg₹2,08,000
  • Sand1.816 cft/sqft1,453 cft₹87,168
  • Aggregate1.35 cft/sqft1,080 cft₹54,000
  • Bricks8 nos/sqft6,400 nos₹51,200
  • Tiles1.3 sqft/sqft1,040 sqft₹57,200
  • Paint0.18 litre/sqft144 litre₹36,000

Cost by stage

  • Site preparation & excavation₹40,800
  • Foundation & plinth₹1,63,200
  • RCC structure (columns, beams, slabs)₹3,40,000
  • Brickwork₹1,36,000
  • Plastering₹81,600
  • Flooring & tiling₹1,08,800
  • Doors & windows₹1,08,800
  • Electrical₹81,600
  • Plumbing & sanitary₹95,200
  • Painting₹68,000
  • Waterproofing₹27,200
  • Staircase, parapet & misc.₹40,800
  • Contingency₹68,000

Cost split

  • Materials · 60%₹8,16,000
  • Labour · 30%₹4,08,000
  • Equipment, transport & misc. · 5%₹68,000
  • Contingency · 5%₹68,000

Suggested payment schedule

MilestoneShareAmount
On agreement / booking10%₹1,36,000
Foundation complete15%₹2,04,000
Plinth complete10%₹1,36,000
Ground floor – slab cast30%₹4,08,000
Brickwork10%₹1,36,000
Plaster & flooring complete15%₹2,04,000
Finishing & handover10%₹1,36,000

Step-by-step working

  1. 1
    Built-up area
    800 sqft × 1 floor(s)
    800 sqft
  2. 2
    Rate per sqft
    ₹1,700 (standard) × 1 (location)
    ₹1,700/sqft
  3. 3
    Total cost
    800 × ₹1,700
    ₹13,60,000
  4. 4
    Cement
    800 × 0.4 bags/sqft
    320 bags
  5. 5
    Steel
    800 × 4 kg/sqft
    3200 kg
  6. 6
    Sand
    800 × 1.816 cft/sqft
    1452.8 cft
  7. 7
    Aggregate
    800 × 1.35 cft/sqft
    1080 cft
  8. 8
    Bricks
    800 × 8 nos/sqft
    6400 nos

Assumptions

  • Thumb-rule (area based) estimate for an RCC framed house; ±10% accuracy.
  • Base rate ₹1,700/sqft for standard quality, location factor 1.
  • Includes structure, masonry, plaster, flooring, doors/windows, electrical, plumbing, painting, waterproofing.
  • Excludes land, approvals, interiors, furniture, compound wall, borewell, water tank.
  • For a detailed BOQ with measurement book, use the plan-based Detailed Estimate.
Need an item-wise BOQ with measurement book, BBS and a drawn plan? Use the Item-wise House BOQ →

Construction cost by built-up area

Frequently asked questions

What is the cost of constructing a 800 sq ft house?

About ₹13.6 lakh at standard finish (₹1,700 per sq ft), ₹11.6 lakh basic and ₹19.2 lakh premium, in a tier-2 city, material and labour together. Metros are about 15% higher, small towns about 8% lower.

How many cement bags are needed for 800 sq ft?

About 320 bags (0.4 bag per sq ft of built-up area) for the whole house — foundation, frame, brickwork, plaster and flooring.

How much steel is needed for 800 sq ft?

About 3,200 kg (3.2 tonnes) at 4 kg per sq ft for an RCC framed house. The structural drawing and bar bending schedule give the exact figure.

Is 800 sq ft the plot size or the built-up area?

These figures are for 800 sq ft of built-up area — the total covered floor area of all floors, measured to the outside of the walls. A G+1 house of 400 sq ft per floor is also 800 sq ft.

How much is the labour cost for 800 sq ft?

Labour is about 30% of the total: roughly ₹4.1 lakh for 800 sq ft at standard finish.

Results are preliminary estimates based on standard thumb rules and the inputs given. Final quantities come from drawings and a detailed BOQ. Structural sizes and reinforcement must be checked by a qualified engineer.