800 sq ft House Construction Cost in India (2026): Material & Labour
Building 800 sq ft of built-up area costs about ₹13.6 lakh at standard finish — ₹1,700 per sq ft, material and labour together, in a tier-2 city in 2026. Below: cost by finish level, the material you will buy, what each stage costs, and a calculator to change area, floors and city.
- Standard cost
- ₹13.6 lakh
- Rate
- ₹1,700/sq ft
- Cement
- 320 bags
- Steel
- 3.2 tonnes
Cost by finish level
| Finish | Rate per sq ft | Total | Range ±10% |
|---|---|---|---|
| Basic | ₹1,450 | ₹11.6 lakh | ₹10.4 lakh – ₹12.8 lakh |
| Standard | ₹1,700 | ₹13.6 lakh | ₹12.2 lakh – ₹15.0 lakh |
| Premium | ₹2,400 | ₹19.2 lakh | ₹17.3 lakh – ₹21.1 lakh |
Material for a 800 sq ft house
| Material | Per sq ft | Quantity | Approx. cost |
|---|---|---|---|
| Cement | 0.4 bags | 320 bags | ₹1,21,600 |
| Steel | 4 kg | 3,200 kg | ₹2,08,000 |
| Sand | 1.816 cft | 1,453 cft | ₹87,168 |
| Aggregate | 1.35 cft | 1,080 cft | ₹54,000 |
| Bricks | 8 nos | 6,400 nos | ₹51,200 |
| Tiles | 1.3 sqft | 1,040 sqft | ₹57,200 |
| Paint | 0.18 litre | 144 litre | ₹36,000 |
Stage-wise cost
| Stage | Share | Amount |
|---|---|---|
| Site preparation & excavation | 3% | ₹40,800 |
| Foundation & plinth | 12% | ₹1,63,200 |
| RCC structure (columns, beams, slabs) | 25% | ₹3,40,000 |
| Brickwork | 10% | ₹1,36,000 |
| Plastering | 6% | ₹81,600 |
| Flooring & tiling | 8% | ₹1,08,800 |
| Doors & windows | 8% | ₹1,08,800 |
| Electrical | 6% | ₹81,600 |
| Plumbing & sanitary | 7% | ₹95,200 |
| Painting | 5% | ₹68,000 |
| Waterproofing | 2% | ₹27,200 |
| Staircase, parapet & misc. | 3% | ₹40,800 |
| Contingency | 5% | ₹68,000 |
Change area, floors, finish or city
Start with your built-up area
Enter the area you will build on each floor, rather than the full plot area. Example: 1,000 sq ft per floor with G+1 means 2,000 sq ft in total. The starting numbers are examples; results update as you edit.
G = ground floor only · G+1 = ground + first floor
- per sqft
- ₹1,700
- Built-up
- 800 sqft
- Approx. construction time
- ~7 months
Likely range (±10%): ₹12,24,000 – ₹14,96,000
Materials needed
Change any rate to see your own cost.
- MaterialThumb rule / sqftQuantityRate (₹)Amount
- Cement0.4 bags/sqft0.4 bags320 bags₹1,21,600
- Steel4 kg/sqft4 kg3,200 kg₹2,08,000
- Sand1.816 cft/sqft1.816 cft1,453 cft₹87,168
- Aggregate1.35 cft/sqft1.35 cft1,080 cft₹54,000
- Bricks8 nos/sqft8 nos6,400 nos₹51,200
- Tiles1.3 sqft/sqft1.3 sqft1,040 sqft₹57,200
- Paint0.18 litre/sqft0.18 litre144 litre₹36,000
Cost by stage
- Site preparation & excavation₹40,800
- Foundation & plinth₹1,63,200
- RCC structure (columns, beams, slabs)₹3,40,000
- Brickwork₹1,36,000
- Plastering₹81,600
- Flooring & tiling₹1,08,800
- Doors & windows₹1,08,800
- Electrical₹81,600
- Plumbing & sanitary₹95,200
- Painting₹68,000
- Waterproofing₹27,200
- Staircase, parapet & misc.₹40,800
- Contingency₹68,000
Cost split
- Materials · 60%₹8,16,000
- Labour · 30%₹4,08,000
- Equipment, transport & misc. · 5%₹68,000
- Contingency · 5%₹68,000
Suggested payment schedule
| Milestone | Share | Amount |
|---|---|---|
| On agreement / booking | 10% | ₹1,36,000 |
| Foundation complete | 15% | ₹2,04,000 |
| Plinth complete | 10% | ₹1,36,000 |
| Ground floor – slab cast | 30% | ₹4,08,000 |
| Brickwork | 10% | ₹1,36,000 |
| Plaster & flooring complete | 15% | ₹2,04,000 |
| Finishing & handover | 10% | ₹1,36,000 |
Step-by-step working
- 1Built-up area800 sqft × 1 floor(s)800 sqft
- 2Rate per sqft₹1,700 (standard) × 1 (location)₹1,700/sqft
- 3Total cost800 × ₹1,700₹13,60,000
- 4Cement800 × 0.4 bags/sqft320 bags
- 5Steel800 × 4 kg/sqft3200 kg
- 6Sand800 × 1.816 cft/sqft1452.8 cft
- 7Aggregate800 × 1.35 cft/sqft1080 cft
- 8Bricks800 × 8 nos/sqft6400 nos
Assumptions
- Thumb-rule (area based) estimate for an RCC framed house; ±10% accuracy.
- Base rate ₹1,700/sqft for standard quality, location factor 1.
- Includes structure, masonry, plaster, flooring, doors/windows, electrical, plumbing, painting, waterproofing.
- Excludes land, approvals, interiors, furniture, compound wall, borewell, water tank.
- For a detailed BOQ with measurement book, use the plan-based Detailed Estimate.
Construction cost by built-up area
Frequently asked questions
What is the cost of constructing a 800 sq ft house?
About ₹13.6 lakh at standard finish (₹1,700 per sq ft), ₹11.6 lakh basic and ₹19.2 lakh premium, in a tier-2 city, material and labour together. Metros are about 15% higher, small towns about 8% lower.
How many cement bags are needed for 800 sq ft?
About 320 bags (0.4 bag per sq ft of built-up area) for the whole house — foundation, frame, brickwork, plaster and flooring.
How much steel is needed for 800 sq ft?
About 3,200 kg (3.2 tonnes) at 4 kg per sq ft for an RCC framed house. The structural drawing and bar bending schedule give the exact figure.
Is 800 sq ft the plot size or the built-up area?
These figures are for 800 sq ft of built-up area — the total covered floor area of all floors, measured to the outside of the walls. A G+1 house of 400 sq ft per floor is also 800 sq ft.
How much is the labour cost for 800 sq ft?
Labour is about 30% of the total: roughly ₹4.1 lakh for 800 sq ft at standard finish.
Results are preliminary estimates based on standard thumb rules and the inputs given. Final quantities come from drawings and a detailed BOQ. Structural sizes and reinforcement must be checked by a qualified engineer.