House Construction Checklist: 82 Points from Plot to Handover
The main 82 things to check, in the order they come up. Tick them as you go (ticks stay in this browser), and open the YouTube videos with each point to see how the work should be done — useful even when the engineer is not on site.
0 of 82 checked
Send on WhatsAppStage 1 · Before buying the plot
- 1.Sale deed in the seller's name and a clean chain of earlier deedsWatch videos on YouTube
- 2.Name in the land record (khasra / khatauni / 7-12) and mutation possibleWatch videos on YouTube
- 3.Diversion (NA) order and the approved colony layoutWatch videos on YouTube
- 4.No loan or court case on the land (encumbrance certificate)Watch videos on YouTube
- 5.Measure the plot and boundaries on site and match the deedWatch videos on YouTube
- 6.Check the master plan: is the road going to be widened?Watch videos on YouTube
- 7.No high-tension line overhead, no height limit near an airport or monumentWatch videos on YouTube
- 8.Does water stand here in the rains? Is it filled-up land (old pond or drain)?Watch videos on YouTube
- 9.Road width, which way the plot faces, plot shapeWatch videos on YouTube
- 10.Power, water and sewer lines reach the plotWatch videos on YouTube
- 11.Ground water: depth and whether it is sweet or saltyWatch videos on YouTube
- 12.Ask how much you may build: setbacks and FAR / FSIWatch videos on YouTubeWork it out →
Stage 2 · Plan and design
- 13.Family needs: BHK, a bedroom downstairs for elders, a floor to rentWatch videos on YouTubeWork it out →
- 14.Adding floors later? Design footings and columns for them nowWatch videos on YouTube
- 15.Soil test before the foundation designWatch videos on YouTube
- 16.Structural drawing and BBS from a registered engineer, as per the earthquake zoneWatch videos on YouTubeWork it out →
- 17.Plinth at least 1.5–2 ft above the roadWatch videos on YouTube
- 18.Drainage slopes to the road drain or sewer; else a septic tankWatch videos on YouTube
- 19.Car parking about 10 × 17 ft with an easy rampWatch videos on YouTube
- 20.Stair placed so an upper floor can be reached on its ownWatch videos on YouTube
- 21.Light and cross ventilation in every room; deep sunshades on south and westWatch videos on YouTube
- 22.Kitchen and toilets close together and stacked floor over floorWatch videos on YouTube
- 23.Vastu decided before the drawing, not afterWatch videos on YouTubeWork it out →
- 24.Electrical load, number of points, inverter wiring, earthing and RCCBWatch videos on YouTube
- 25.Piping for AC, solar, EV charging, CCTV and internet laid in advanceWatch videos on YouTube
- 26.G+2 or more: leave space for a liftWatch videos on YouTube
- 27.Overhead tank height, sump and rainwater harvestingWatch videos on YouTube
- 28.Roof heat protection (insulation or heat-reflective tiles)Watch videos on YouTube
- 29.Get the building plan passedWatch videos on YouTube
- 30.Fix tiles, sanitary, doors, windows and kitchen drawing before plasterWatch videos on YouTube
Stage 3 · Budget, loan and contractor
- 31.Rough cost by rate per sq ft, then an item-wise BOQ from the planWatch videos on YouTubeWork it out →
- 32.Material quantities: cement, steel, sand, aggregate, bricksWatch videos on YouTubeWork it out →
- 33.Keep 8–10% extraWatch videos on YouTube
- 34.Add hidden costs: approvals, connections, fees, transport, boundary, borewell, interiorsWatch videos on YouTube
- 35.Home loan stages, pre-EMI and tax benefitWatch videos on YouTube
- 36.Insurance during constructionWatch videos on YouTube
- 37.Contract type: labour only or turnkeyWatch videos on YouTubeWork it out →
- 38.See the contractor's old work and talk to old clientsWatch videos on YouTube
- 39.2–3 quotes, matched to the BOQ, GST written clearlyWatch videos on YouTubeWork it out →
- 40.Agreement: drawings, brands, grades, finish rates, time, penalty for delayWatch videos on YouTube
- 41.Pay by stage, no big advanceWatch videos on YouTube
- 42.Hold back the last 5% for leaks and cracksWatch videos on YouTube
Stage 4 · During construction
- 43.Cement: brand, not older than 3 months, stored dryWatch videos on YouTube
- 44.Steel: Fe500D, ISI mark, test certificate, weigh the bundles, no flaky rustWatch videos on YouTube
- 45.Sand without silt, right-size aggregate, no salty waterWatch videos on YouTube
- 46.Count or weigh every delivery; guard the siteWatch videos on YouTube
- 47.Dig to firm soil; check layout diagonals before diggingWatch videos on YouTubeWork it out →
- 48.Anti-termite treatment before the foundationWatch videos on YouTube
- 49.PCC, footing to drawing size, 50 mm cover, no concreting in standing waterWatch videos on YouTube
- 50.Plinth beam, backfill compacted in layers, DPCWatch videos on YouTube
- 51.Column bars: number and diameter as per drawingWatch videos on YouTube
- 52.Laps in the middle half, staggered, 50 × bar diameter longWatch videos on YouTube
- 53.Ties close, 135° hooks, ties also inside the beam-column jointWatch videos on YouTube
- 54.Columns in plumb, no column standing on a beamWatch videos on YouTube
- 55.Clean the column base before casting; never cut a column laterWatch videos on YouTube
- 56.Beam bars anchored into the column, extra top bars at supportsWatch videos on YouTube
- 57.Stirrups closer near columns; full beam depthWatch videos on YouTube
- 58.Slab top steel on chairs so it is not trodden downWatch videos on YouTube
- 59.Main bars of sunshades and balconies at the topWatch videos on YouTube
- 60.Full slab thickness, cover blocks underneathWatch videos on YouTube
- 61.Stair bars crossed at the inner corner, main bars at the bottomWatch videos on YouTube
- 62.No welding or heating of bars to bend themWatch videos on YouTube
- 63.Right mix (M20 ≈ 1:1.5:3), machine mixed, little waterWatch videos on YouTube
- 64.Place within 30–45 minutes, no dropping from height, vibrator alwaysWatch videos on YouTube
- 65.Cast in one go; if stopped, the joint in the right placeWatch videos on YouTube
- 66.Cube samples from every pour, tested at 7 and 28 daysWatch videos on YouTube
- 67.Cure 7–10 days; props 7–14 days; no load on a fresh slabWatch videos on YouTubeWork it out →
- 68.No heavy wall on a slab without a beamWatch videos on YouTube
- 69.Lintels and earthquake band; mesh at brick-column jointsWatch videos on YouTubeWork it out →
- 70.Test wiring and plumbing before plaster; inspection chambers on drainsWatch videos on YouTube
- 71.Waterproof roof, toilets, balconies and tank before tilingWatch videos on YouTube
- 72.Check before every pour (or get an engineer) and photograph the steelWatch videos on YouTube
- 73.Foundation and plinth done before the monsoonWatch videos on YouTube
- 74.Labour safety; talk to neighbours firstWatch videos on YouTube
Stage 5 · Handover and after
- 75.Floor slopes, hollow tiles, doors and windows closing wellWatch videos on YouTube
- 76.Leak test with water (roof, toilets, tank)Watch videos on YouTube
- 77.Every electrical point, earthing and MCBsWatch videos on YouTube
- 78.Railings, 3.5 ft parapet, equal stair stepsWatch videos on YouTube
- 79.Completion certificate, permanent connections, property taxWatch videos on YouTube
- 80.Keep a file: drawings, BOQ, bills, warranties, test reports, photosWatch videos on YouTube
- 81.Wide or diagonal cracks: show an engineerWatch videos on YouTube
- 82.Before adding floors or heavy tanks / towers on the roof, get it checkedWatch videos on YouTube