How to Make a House Construction Budget and BOQ

Step 4 of 7 · Start with a per-sqft figure, then make an item-wise BOQ from the plan. The BOQ is what you compare contractors against.

Start with a rough figure: built-up area × rate per sq ft. In a tier-2 city in 2026 that is about ₹1,450 (basic), ₹1,700 (standard) or ₹2,400 (premium) per sq ft, material and labour together. This tells you whether the plan fits your money before anything is drawn in detail.

Once the plan is final, make an item-wise BOQ (bill of quantities): every item measured from the drawing and priced — excavation, PCC, footings, columns, beams, slabs, brickwork, plaster, flooring, doors, windows, electrical, plumbing, paint. The BOQ is what you compare contractors' quotes against and what you check running bills with.

Keep 8–10% on top for price rises and changes. Land, approvals, architect fees, interiors, furniture, compound wall, borewell and water tank are usually outside the per-sq-ft rate — list them separately so they don't surprise you at the end.

Checklist

Common mistakes

  • Taking a per-sq-ft quote without knowing what it includes.
  • Spending the whole budget on the structure and running short at finishing.
  • Buying all material at once without a stage-wise plan, and losing some to theft or weather.

Results are preliminary estimates based on standard thumb rules and the inputs given. Final quantities come from drawings and a detailed BOQ. Structural sizes and reinforcement must be checked by a qualified engineer.