How to Make a House Construction Budget and BOQ
Step 4 of 7 · Start with a per-sqft figure, then make an item-wise BOQ from the plan. The BOQ is what you compare contractors against.
Start with a rough figure: built-up area × rate per sq ft. In a tier-2 city in 2026 that is about ₹1,450 (basic), ₹1,700 (standard) or ₹2,400 (premium) per sq ft, material and labour together. This tells you whether the plan fits your money before anything is drawn in detail.
Once the plan is final, make an item-wise BOQ (bill of quantities): every item measured from the drawing and priced — excavation, PCC, footings, columns, beams, slabs, brickwork, plaster, flooring, doors, windows, electrical, plumbing, paint. The BOQ is what you compare contractors' quotes against and what you check running bills with.
Keep 8–10% on top for price rises and changes. Land, approvals, architect fees, interiors, furniture, compound wall, borewell and water tank are usually outside the per-sq-ft rate — list them separately so they don't surprise you at the end.
Checklist
- Rough cost: built-up area × rate per sqft (finish level and city change the rate).▶ Watch videos on YouTubeWork it out →
- Detailed BOQ: every item measured — excavation, concrete, steel, brickwork, plaster, flooring, doors, windows, electrical, plumbing, paint.▶ Watch videos on YouTubeWork it out →
- Material quantities — cement bags, steel kg, sand, aggregate, bricks — so you can buy in time and check deliveries.▶ Watch videos on YouTubeWork it out →
- Keep 8–10% extra for price rises and changes; land, approvals, interiors and furniture are on top.▶ Watch videos on YouTube
- Cash flow: how much money is needed at each stage, and the loan EMI or pre-EMI during construction.▶ Watch videos on YouTubeWork it out →
Common mistakes
- Taking a per-sq-ft quote without knowing what it includes.
- Spending the whole budget on the structure and running short at finishing.
- Buying all material at once without a stage-wise plan, and losing some to theft or weather.