When to Remove Slab and Beam Shuttering (IS 456)
Short answer
As per IS 456 with ordinary cement: slab bottom sheets after 3 days with props left in, slab props after 7 days (span up to 4.5 m) or 14 days (longer spans), beam props after 14 days (up to 6 m).
IS 456 gives these minimum times for ordinary Portland cement in normal weather: vertical formwork of columns, walls and beam sides 16–24 hours; slab bottom sheets 3 days with props left in; slab props 7 days (span up to 4.5 m) or 14 days (longer); beam bottom props 14 days (span up to 6 m) or 21 days (longer).
In cold weather or with PPC / slag cement, concrete gains strength more slowly, so keep the props longer. Never load a fresh slab with bricks or cement bags before the props come out.