Thumb rules are for checking, not for designing. Use them to see in a minute whether a supplier's bill, a contractor's claim or your own estimate is in the right range; then work out the real quantity from the drawing.
Concrete volume in a drawing is wet volume; the dry material you buy is about 1.54 times that. For M20 (1:1.5:3) one cubic metre needs about 8 bags of cement, 0.42 m³ of sand and 0.84 m³ of aggregate.
Steel is ordered by weight but shown on drawings by length and diameter. Weight per metre is d²/162 kg with d in mm — so a 12 mm bar of 12 m weighs about 10.7 kg.
Checklist
- Per sqft of built-up area (RCC house): cement ≈ 0.4 bag, steel ≈ 4 kg, sand ≈ 1.8 cft, aggregate ≈ 1.35 cft, bricks ≈ 8.▶ Watch videos on YouTubeWork it out →
- Concrete mixes: M15 ≈ 1:2:4, M20 ≈ 1:1.5:3; dry volume = wet volume × 1.54; one cement bag = 50 kg = 0.0347 m³.▶ Watch videos on YouTubeWork it out →
- Steel weight per metre = d²/162 kg (d in mm): 8 mm 0.395, 10 mm 0.617, 12 mm 0.889, 16 mm 1.58 kg/m.▶ Watch videos on YouTubeWork it out →
- Clear cover: footing 50 mm, column 40 mm, beam 25 mm, slab 20 mm; lap length about 50 × bar diameter.▶ Watch videos on YouTube
- Brickwork: about 500 bricks per m³ (9-inch wall); plaster 12 mm inside (1:6), 20 mm outside (1:4).▶ Watch videos on YouTubeWork it out →
- Units: 1 m = 3.281 ft, 1 m² = 10.764 sqft, 1 m³ = 35.31 cft, 1 gaj (sq yard) = 9 sqft.▶ Watch videos on YouTubeWork it out →
Common mistakes
- Ordering material from a thumb rule without checking it against the drawing.
- Mixing up wet and dry volume, or sq ft and sq m.
- Forgetting laps and wastage (3–5%) in the steel order.