GGuniyo

Excavation Calculator – Volume, Brass and Cost

Enter pit or trench size, depth and number, and the working space around it. You get the excavation volume in m³, cft and brass, the loose soil to dispose and the cost.

Units
m
m
m
nos
m
%

Result

Preliminary estimate
Volume
86.64 m³
3059.67 cft
Brass
30.6
Loose soil
108.3 m³
Cost
₹24,259

Step-by-step working

  1. 1
    Size with working space
    (1.5 + 2×0.2) × (1.5 + 2×0.2)
    1.9 × 1.9 m
  2. 2
    Excavation volume
    1.9 × 1.9 × 1.5 × 16
    86.64 m³
  3. 3
    In cft / brass
    86.64 × 35.315
    3059.7 cft = 30.6 brass
  4. 4
    Loose soil to dispose
    86.64 × (1 + 25%)
    108.3 m³

Assumptions

  • Working space 0.2 m each side.
  • Soil bulking 25% (ordinary soil 20–30%, rock more).
  • Vertical sides assumed; add for slopes / shoring in deep or loose soil.

Frequently asked questions

What is 1 brass?

1 brass = 100 cft = 2.83 m³. It is commonly used in India for excavation, sand and aggregate.

Why add working space?

Workers need room to fix shuttering and work around the footing, usually 150–300 mm on each side.

Why is loose soil more than the pit volume?

Excavated soil bulks up by about 20–30% in ordinary soil, so more truck loads are needed than the pit volume suggests.