Building 600 sq ft of built-up area costs about ₹10.2 lakh at standard finish — ₹1,700 per sq ft, material and labour together, in a tier-2 city in 2026. Below: cost by finish level, the material you will buy, what each stage costs, and a calculator to change area, floors and city.

Standard cost
₹10.2 lakh
Rate
₹1,700/sq ft
Cement
240 bags
Steel
2.4 tonnes

Cost by finish level

FinishRate per sq ftTotalRange ±10%
Basic₹1,450₹8.7 lakh₹7.8 lakh – ₹9.6 lakh
Standard₹1,700₹10.2 lakh₹9.2 lakh – ₹11.2 lakh
Premium₹2,400₹14.4 lakh₹13.0 lakh – ₹15.8 lakh

Material for a 600 sq ft house

MaterialPer sq ftQuantityApprox. cost
Cement0.4 bags240 bags₹91,200
Steel4 kg2,400 kg₹1,56,000
Sand1.816 cft1,090 cft₹65,376
Aggregate1.35 cft810 cft₹40,500
Bricks8 nos4,800 nos₹38,400
Tiles1.3 sqft780 sqft₹42,900
Paint0.18 litre108 litre₹27,000

Stage-wise cost

StageShareAmount
Site preparation & excavation3%₹30,600
Foundation & plinth12%₹1,22,400
RCC structure (columns, beams, slabs)25%₹2,55,000
Brickwork10%₹1,02,000
Plastering6%₹61,200
Flooring & tiling8%₹81,600
Doors & windows8%₹81,600
Electrical6%₹61,200
Plumbing & sanitary7%₹71,400
Painting5%₹51,000
Waterproofing2%₹20,400
Staircase, parapet & misc.3%₹30,600
Contingency5%₹51,000

Change area, floors, finish or city

Start with your built-up area

Enter the area you will build on each floor, rather than the full plot area. Example: 1,000 sq ft per floor with G+1 means 2,000 sq ft in total. The starting numbers are examples; results update as you edit.

sqft

G = ground floor only · G+1 = ground + first floor

Floors
Quality
₹
Enter your local rate if you know it
Total estimated costPreliminary estimate
₹10,20,000
≈ ₹10.2 lakh
per sqft
₹1,700
Built-up
600 sqft
Approx. construction time
~7 months

Likely range (±10%): ₹9,18,000 – ₹11,22,000

Materials needed

Change any rate to see your own cost.

  • Cement0.4 bags/sqft240 bags₹91,200
  • Steel4 kg/sqft2,400 kg₹1,56,000
  • Sand1.816 cft/sqft1,090 cft₹65,376
  • Aggregate1.35 cft/sqft810 cft₹40,500
  • Bricks8 nos/sqft4,800 nos₹38,400
  • Tiles1.3 sqft/sqft780 sqft₹42,900
  • Paint0.18 litre/sqft108 litre₹27,000

Cost by stage

  • Site preparation & excavation₹30,600
  • Foundation & plinth₹1,22,400
  • RCC structure (columns, beams, slabs)₹2,55,000
  • Brickwork₹1,02,000
  • Plastering₹61,200
  • Flooring & tiling₹81,600
  • Doors & windows₹81,600
  • Electrical₹61,200
  • Plumbing & sanitary₹71,400
  • Painting₹51,000
  • Waterproofing₹20,400
  • Staircase, parapet & misc.₹30,600
  • Contingency₹51,000

Cost split

  • Materials · 60%₹6,12,000
  • Labour · 30%₹3,06,000
  • Equipment, transport & misc. · 5%₹51,000
  • Contingency · 5%₹51,000

Suggested payment schedule

MilestoneShareAmount
On agreement / booking10%₹1,02,000
Foundation complete15%₹1,53,000
Plinth complete10%₹1,02,000
Ground floor – slab cast30%₹3,06,000
Brickwork10%₹1,02,000
Plaster & flooring complete15%₹1,53,000
Finishing & handover10%₹1,02,000

Step-by-step working

  1. 1
    Built-up area
    600 sqft × 1 floor(s)
    600 sqft
  2. 2
    Rate per sqft
    ₹1,700 (standard) × 1 (location)
    ₹1,700/sqft
  3. 3
    Total cost
    600 × ₹1,700
    ₹10,20,000
  4. 4
    Cement
    600 × 0.4 bags/sqft
    240 bags
  5. 5
    Steel
    600 × 4 kg/sqft
    2400 kg
  6. 6
    Sand
    600 × 1.816 cft/sqft
    1089.6 cft
  7. 7
    Aggregate
    600 × 1.35 cft/sqft
    810 cft
  8. 8
    Bricks
    600 × 8 nos/sqft
    4800 nos

Assumptions

  • Thumb-rule (area based) estimate for an RCC framed house; ±10% accuracy.
  • Base rate ₹1,700/sqft for standard quality, location factor 1.
  • Includes structure, masonry, plaster, flooring, doors/windows, electrical, plumbing, painting, waterproofing.
  • Excludes land, approvals, interiors, furniture, compound wall, borewell, water tank.
  • For a detailed BOQ with measurement book, use the plan-based Detailed Estimate.
Need an item-wise BOQ with measurement book, BBS and a drawn plan? Use the Item-wise House BOQ →

Construction cost by built-up area

Frequently asked questions

What is the cost of constructing a 600 sq ft house?

About ₹10.2 lakh at standard finish (₹1,700 per sq ft), ₹8.7 lakh basic and ₹14.4 lakh premium, in a tier-2 city, material and labour together. Metros are about 15% higher, small towns about 8% lower.

How many cement bags are needed for 600 sq ft?

About 240 bags (0.4 bag per sq ft of built-up area) for the whole house — foundation, frame, brickwork, plaster and flooring.

How much steel is needed for 600 sq ft?

About 2,400 kg (2.4 tonnes) at 4 kg per sq ft for an RCC framed house. The structural drawing and bar bending schedule give the exact figure.

Is 600 sq ft the plot size or the built-up area?

These figures are for 600 sq ft of built-up area — the total covered floor area of all floors, measured to the outside of the walls. A G+1 house of 300 sq ft per floor is also 600 sq ft.

How much is the labour cost for 600 sq ft?

Labour is about 30% of the total: roughly ₹3.1 lakh for 600 sq ft at standard finish.