Building 500 sq ft of built-up area costs about ₹8.5 lakh at standard finish — ₹1,700 per sq ft, material and labour together, in a tier-2 city in 2026. Below: cost by finish level, the material you will buy, what each stage costs, and a calculator to change area, floors and city.

Standard cost
₹8.5 lakh
Rate
₹1,700/sq ft
Cement
200 bags
Steel
2 tonnes

Cost by finish level

FinishRate per sq ftTotalRange ±10%
Basic₹1,450₹7.3 lakh₹6.5 lakh – ₹8.0 lakh
Standard₹1,700₹8.5 lakh₹7.7 lakh – ₹9.4 lakh
Premium₹2,400₹12.0 lakh₹10.8 lakh – ₹13.2 lakh

Material for a 500 sq ft house

MaterialPer sq ftQuantityApprox. cost
Cement0.4 bags200 bags₹76,000
Steel4 kg2,000 kg₹1,30,000
Sand1.816 cft908 cft₹54,480
Aggregate1.35 cft675 cft₹33,750
Bricks8 nos4,000 nos₹32,000
Tiles1.3 sqft650 sqft₹35,750
Paint0.18 litre90 litre₹22,500

Stage-wise cost

StageShareAmount
Site preparation & excavation3%₹25,500
Foundation & plinth12%₹1,02,000
RCC structure (columns, beams, slabs)25%₹2,12,500
Brickwork10%₹85,000
Plastering6%₹51,000
Flooring & tiling8%₹68,000
Doors & windows8%₹68,000
Electrical6%₹51,000
Plumbing & sanitary7%₹59,500
Painting5%₹42,500
Waterproofing2%₹17,000
Staircase, parapet & misc.3%₹25,500
Contingency5%₹42,500

Change area, floors, finish or city

Start with your built-up area

Enter the area you will build on each floor, rather than the full plot area. Example: 1,000 sq ft per floor with G+1 means 2,000 sq ft in total. The starting numbers are examples; results update as you edit.

sqft

G = ground floor only · G+1 = ground + first floor

Floors
Quality
₹
Enter your local rate if you know it
Total estimated costPreliminary estimate
₹8,50,000
≈ ₹8.5 lakh
per sqft
₹1,700
Built-up
500 sqft
Approx. construction time
~7 months

Likely range (±10%): ₹7,65,000 – ₹9,35,000

Materials needed

Change any rate to see your own cost.

  • Cement0.4 bags/sqft200 bags₹76,000
  • Steel4 kg/sqft2,000 kg₹1,30,000
  • Sand1.816 cft/sqft908 cft₹54,480
  • Aggregate1.35 cft/sqft675 cft₹33,750
  • Bricks8 nos/sqft4,000 nos₹32,000
  • Tiles1.3 sqft/sqft650 sqft₹35,750
  • Paint0.18 litre/sqft90 litre₹22,500

Cost by stage

  • Site preparation & excavation₹25,500
  • Foundation & plinth₹1,02,000
  • RCC structure (columns, beams, slabs)₹2,12,500
  • Brickwork₹85,000
  • Plastering₹51,000
  • Flooring & tiling₹68,000
  • Doors & windows₹68,000
  • Electrical₹51,000
  • Plumbing & sanitary₹59,500
  • Painting₹42,500
  • Waterproofing₹17,000
  • Staircase, parapet & misc.₹25,500
  • Contingency₹42,500

Cost split

  • Materials · 60%₹5,10,000
  • Labour · 30%₹2,55,000
  • Equipment, transport & misc. · 5%₹42,500
  • Contingency · 5%₹42,500

Suggested payment schedule

MilestoneShareAmount
On agreement / booking10%₹85,000
Foundation complete15%₹1,27,500
Plinth complete10%₹85,000
Ground floor – slab cast30%₹2,55,000
Brickwork10%₹85,000
Plaster & flooring complete15%₹1,27,500
Finishing & handover10%₹85,000

Step-by-step working

  1. 1
    Built-up area
    500 sqft × 1 floor(s)
    500 sqft
  2. 2
    Rate per sqft
    ₹1,700 (standard) × 1 (location)
    ₹1,700/sqft
  3. 3
    Total cost
    500 × ₹1,700
    ₹8,50,000
  4. 4
    Cement
    500 × 0.4 bags/sqft
    200 bags
  5. 5
    Steel
    500 × 4 kg/sqft
    2000 kg
  6. 6
    Sand
    500 × 1.816 cft/sqft
    908 cft
  7. 7
    Aggregate
    500 × 1.35 cft/sqft
    675 cft
  8. 8
    Bricks
    500 × 8 nos/sqft
    4000 nos

Assumptions

  • Thumb-rule (area based) estimate for an RCC framed house; ±10% accuracy.
  • Base rate ₹1,700/sqft for standard quality, location factor 1.
  • Includes structure, masonry, plaster, flooring, doors/windows, electrical, plumbing, painting, waterproofing.
  • Excludes land, approvals, interiors, furniture, compound wall, borewell, water tank.
  • For a detailed BOQ with measurement book, use the plan-based Detailed Estimate.
Need an item-wise BOQ with measurement book, BBS and a drawn plan? Use the Item-wise House BOQ →

Construction cost by built-up area

Frequently asked questions

What is the cost of constructing a 500 sq ft house?

About ₹8.5 lakh at standard finish (₹1,700 per sq ft), ₹7.3 lakh basic and ₹12.0 lakh premium, in a tier-2 city, material and labour together. Metros are about 15% higher, small towns about 8% lower.

How many cement bags are needed for 500 sq ft?

About 200 bags (0.4 bag per sq ft of built-up area) for the whole house — foundation, frame, brickwork, plaster and flooring.

How much steel is needed for 500 sq ft?

About 2,000 kg (2 tonnes) at 4 kg per sq ft for an RCC framed house. The structural drawing and bar bending schedule give the exact figure.

Is 500 sq ft the plot size or the built-up area?

These figures are for 500 sq ft of built-up area — the total covered floor area of all floors, measured to the outside of the walls. A G+1 house of 250 sq ft per floor is also 500 sq ft.

How much is the labour cost for 500 sq ft?

Labour is about 30% of the total: roughly ₹2.5 lakh for 500 sq ft at standard finish.

Results are preliminary estimates based on standard thumb rules and the inputs given. Final quantities come from drawings and a detailed BOQ. Structural sizes and reinforcement must be checked by a qualified engineer.