Choosing a House Contractor and Writing the Agreement
Step 5 of 7 · Most fights on site come from what was never written down.
In a labour-only contract you buy the material and the contractor supplies the workers; you control quality but must be on site often. In a material-plus-labour (turnkey) contract the contractor does everything for a rate per sq ft; it is simpler, but only as good as the specification you write down.
The agreement should name the drawings, the brands and grades of every material, the finish items (tile size and price, door type, number of electrical points), the time for completion, the payment schedule, and what happens with extra work and delays.
Pay against completed stages — plinth, each slab, brickwork, plaster, flooring, handover — and keep 5% back until a few months after handover for leaks and cracks.
Checklist
- Choose the contract type: labour only (you buy material), or material + labour (turnkey) at a rate per sqft.▶ Watch videos on YouTube
- Write down the brands and grades: cement, steel (Fe500D), tiles, doors, windows, wires, pipes, sanitary and paint.▶ Watch videos on YouTube
- Payments linked to stages (plinth, each slab, brickwork, plaster, finishing), never in advance of the work.▶ Watch videos on YouTube
- Compare the contractor's rate with the market before signing, and keep a measurement book (MB) for running bills.▶ Watch videos on YouTubeWork it out →
Common mistakes
- Giving a large advance before work starts.
- A one-page agreement with only the rate per sq ft.
- Choosing the cheapest quote without checking what was left out of it.
Results are preliminary estimates based on standard thumb rules and the inputs given. Final quantities come from drawings and a detailed BOQ. Structural sizes and reinforcement must be checked by a qualified engineer.