1,500 sq ft House Construction Cost in India (2026): Material & Labour
Building 1,500 sq ft of built-up area costs about ₹25.5 lakh at standard finish — ₹1,700 per sq ft, material and labour together, in a tier-2 city in 2026. Below: cost by finish level, the material you will buy, what each stage costs, and a calculator to change area, floors and city.
- Standard cost
- ₹25.5 lakh
- Rate
- ₹1,700/sq ft
- Cement
- 600 bags
- Steel
- 6 tonnes
Cost by finish level
| Finish | Rate per sq ft | Total | Range ±10% |
|---|---|---|---|
| Basic | ₹1,450 | ₹21.8 lakh | ₹19.6 lakh – ₹23.9 lakh |
| Standard | ₹1,700 | ₹25.5 lakh | ₹22.9 lakh – ₹28.1 lakh |
| Premium | ₹2,400 | ₹36.0 lakh | ₹32.4 lakh – ₹39.6 lakh |
Material for a 1,500 sq ft house
| Material | Per sq ft | Quantity | Approx. cost |
|---|---|---|---|
| Cement | 0.4 bags | 600 bags | ₹2,28,000 |
| Steel | 4 kg | 6,000 kg | ₹3,90,000 |
| Sand | 1.816 cft | 2,724 cft | ₹1,63,440 |
| Aggregate | 1.35 cft | 2,025 cft | ₹1,01,250 |
| Bricks | 8 nos | 12,000 nos | ₹96,000 |
| Tiles | 1.3 sqft | 1,950 sqft | ₹1,07,250 |
| Paint | 0.18 litre | 270 litre | ₹67,500 |
Stage-wise cost
| Stage | Share | Amount |
|---|---|---|
| Site preparation & excavation | 3% | ₹76,500 |
| Foundation & plinth | 12% | ₹3,06,000 |
| RCC structure (columns, beams, slabs) | 25% | ₹6,37,500 |
| Brickwork | 10% | ₹2,55,000 |
| Plastering | 6% | ₹1,53,000 |
| Flooring & tiling | 8% | ₹2,04,000 |
| Doors & windows | 8% | ₹2,04,000 |
| Electrical | 6% | ₹1,53,000 |
| Plumbing & sanitary | 7% | ₹1,78,500 |
| Painting | 5% | ₹1,27,500 |
| Waterproofing | 2% | ₹51,000 |
| Staircase, parapet & misc. | 3% | ₹76,500 |
| Contingency | 5% | ₹1,27,500 |
Change area, floors, finish or city
Start with your built-up area
Enter the area you will build on each floor, rather than the full plot area. Example: 1,000 sq ft per floor with G+1 means 2,000 sq ft in total. The starting numbers are examples; results update as you edit.
G = ground floor only · G+1 = ground + first floor
- per sqft
- ₹1,700
- Built-up
- 1,500 sqft
- Approx. construction time
- ~8 months
Likely range (±10%): ₹22,95,000 – ₹28,05,000
Materials needed
Change any rate to see your own cost.
- MaterialThumb rule / sqftQuantityRate (₹)Amount
- Cement0.4 bags/sqft0.4 bags600 bags₹2,28,000
- Steel4 kg/sqft4 kg6,000 kg₹3,90,000
- Sand1.816 cft/sqft1.816 cft2,724 cft₹1,63,440
- Aggregate1.35 cft/sqft1.35 cft2,025 cft₹1,01,250
- Bricks8 nos/sqft8 nos12,000 nos₹96,000
- Tiles1.3 sqft/sqft1.3 sqft1,950 sqft₹1,07,250
- Paint0.18 litre/sqft0.18 litre270 litre₹67,500
Cost by stage
- Site preparation & excavation₹76,500
- Foundation & plinth₹3,06,000
- RCC structure (columns, beams, slabs)₹6,37,500
- Brickwork₹2,55,000
- Plastering₹1,53,000
- Flooring & tiling₹2,04,000
- Doors & windows₹2,04,000
- Electrical₹1,53,000
- Plumbing & sanitary₹1,78,500
- Painting₹1,27,500
- Waterproofing₹51,000
- Staircase, parapet & misc.₹76,500
- Contingency₹1,27,500
Cost split
- Materials · 60%₹15,30,000
- Labour · 30%₹7,65,000
- Equipment, transport & misc. · 5%₹1,27,500
- Contingency · 5%₹1,27,500
Suggested payment schedule
| Milestone | Share | Amount |
|---|---|---|
| On agreement / booking | 10% | ₹2,55,000 |
| Foundation complete | 15% | ₹3,82,500 |
| Plinth complete | 10% | ₹2,55,000 |
| Ground floor – slab cast | 30% | ₹7,65,000 |
| Brickwork | 10% | ₹2,55,000 |
| Plaster & flooring complete | 15% | ₹3,82,500 |
| Finishing & handover | 10% | ₹2,55,000 |
Step-by-step working
- 1Built-up area1500 sqft × 1 floor(s)1500 sqft
- 2Rate per sqft₹1,700 (standard) × 1 (location)₹1,700/sqft
- 3Total cost1500 × ₹1,700₹25,50,000
- 4Cement1500 × 0.4 bags/sqft600 bags
- 5Steel1500 × 4 kg/sqft6000 kg
- 6Sand1500 × 1.816 cft/sqft2724 cft
- 7Aggregate1500 × 1.35 cft/sqft2025 cft
- 8Bricks1500 × 8 nos/sqft12000 nos
Assumptions
- Thumb-rule (area based) estimate for an RCC framed house; ±10% accuracy.
- Base rate ₹1,700/sqft for standard quality, location factor 1.
- Includes structure, masonry, plaster, flooring, doors/windows, electrical, plumbing, painting, waterproofing.
- Excludes land, approvals, interiors, furniture, compound wall, borewell, water tank.
- For a detailed BOQ with measurement book, use the plan-based Detailed Estimate.
House plans close to 1,500 sq ft
Construction cost by built-up area
Frequently asked questions
What is the cost of constructing a 1,500 sq ft house?
About ₹25.5 lakh at standard finish (₹1,700 per sq ft), ₹21.8 lakh basic and ₹36.0 lakh premium, in a tier-2 city, material and labour together. Metros are about 15% higher, small towns about 8% lower.
How many cement bags are needed for 1,500 sq ft?
About 600 bags (0.4 bag per sq ft of built-up area) for the whole house — foundation, frame, brickwork, plaster and flooring.
How much steel is needed for 1,500 sq ft?
About 6,000 kg (6 tonnes) at 4 kg per sq ft for an RCC framed house. The structural drawing and bar bending schedule give the exact figure.
Is 1,500 sq ft the plot size or the built-up area?
These figures are for 1,500 sq ft of built-up area — the total covered floor area of all floors, measured to the outside of the walls. A G+1 house of 750 sq ft per floor is also 1,500 sq ft.
How much is the labour cost for 1,500 sq ft?
Labour is about 30% of the total: roughly ₹7.7 lakh for 1,500 sq ft at standard finish.
Results are preliminary estimates based on standard thumb rules and the inputs given. Final quantities come from drawings and a detailed BOQ. Structural sizes and reinforcement must be checked by a qualified engineer.