1,500 sq ft House Construction Cost in India (2026): Material & Labour

Building 1,500 sq ft of built-up area costs about ₹25.5 lakh at standard finish — ₹1,700 per sq ft, material and labour together, in a tier-2 city in 2026. Below: cost by finish level, the material you will buy, what each stage costs, and a calculator to change area, floors and city.

Standard cost
₹25.5 lakh
Rate
₹1,700/sq ft
Cement
600 bags
Steel
6 tonnes

Cost by finish level

FinishRate per sq ftTotalRange ±10%
Basic₹1,450₹21.8 lakh₹19.6 lakh – ₹23.9 lakh
Standard₹1,700₹25.5 lakh₹22.9 lakh – ₹28.1 lakh
Premium₹2,400₹36.0 lakh₹32.4 lakh – ₹39.6 lakh

Material for a 1,500 sq ft house

MaterialPer sq ftQuantityApprox. cost
Cement0.4 bags600 bags₹2,28,000
Steel4 kg6,000 kg₹3,90,000
Sand1.816 cft2,724 cft₹1,63,440
Aggregate1.35 cft2,025 cft₹1,01,250
Bricks8 nos12,000 nos₹96,000
Tiles1.3 sqft1,950 sqft₹1,07,250
Paint0.18 litre270 litre₹67,500

Stage-wise cost

StageShareAmount
Site preparation & excavation3%₹76,500
Foundation & plinth12%₹3,06,000
RCC structure (columns, beams, slabs)25%₹6,37,500
Brickwork10%₹2,55,000
Plastering6%₹1,53,000
Flooring & tiling8%₹2,04,000
Doors & windows8%₹2,04,000
Electrical6%₹1,53,000
Plumbing & sanitary7%₹1,78,500
Painting5%₹1,27,500
Waterproofing2%₹51,000
Staircase, parapet & misc.3%₹76,500
Contingency5%₹1,27,500

Change area, floors, finish or city

Start with your built-up area

Enter the area you will build on each floor, rather than the full plot area. Example: 1,000 sq ft per floor with G+1 means 2,000 sq ft in total. The starting numbers are examples; results update as you edit.

sqft

G = ground floor only · G+1 = ground + first floor

Floors
Quality
₹
Enter your local rate if you know it
Total estimated costPreliminary estimate
₹25,50,000
≈ ₹25.5 lakh
per sqft
₹1,700
Built-up
1,500 sqft
Approx. construction time
~8 months

Likely range (±10%): ₹22,95,000 – ₹28,05,000

Materials needed

Change any rate to see your own cost.

  • Cement0.4 bags/sqft600 bags₹2,28,000
  • Steel4 kg/sqft6,000 kg₹3,90,000
  • Sand1.816 cft/sqft2,724 cft₹1,63,440
  • Aggregate1.35 cft/sqft2,025 cft₹1,01,250
  • Bricks8 nos/sqft12,000 nos₹96,000
  • Tiles1.3 sqft/sqft1,950 sqft₹1,07,250
  • Paint0.18 litre/sqft270 litre₹67,500

Cost by stage

  • Site preparation & excavation₹76,500
  • Foundation & plinth₹3,06,000
  • RCC structure (columns, beams, slabs)₹6,37,500
  • Brickwork₹2,55,000
  • Plastering₹1,53,000
  • Flooring & tiling₹2,04,000
  • Doors & windows₹2,04,000
  • Electrical₹1,53,000
  • Plumbing & sanitary₹1,78,500
  • Painting₹1,27,500
  • Waterproofing₹51,000
  • Staircase, parapet & misc.₹76,500
  • Contingency₹1,27,500

Cost split

  • Materials · 60%₹15,30,000
  • Labour · 30%₹7,65,000
  • Equipment, transport & misc. · 5%₹1,27,500
  • Contingency · 5%₹1,27,500

Suggested payment schedule

MilestoneShareAmount
On agreement / booking10%₹2,55,000
Foundation complete15%₹3,82,500
Plinth complete10%₹2,55,000
Ground floor – slab cast30%₹7,65,000
Brickwork10%₹2,55,000
Plaster & flooring complete15%₹3,82,500
Finishing & handover10%₹2,55,000

Step-by-step working

  1. 1
    Built-up area
    1500 sqft × 1 floor(s)
    1500 sqft
  2. 2
    Rate per sqft
    ₹1,700 (standard) × 1 (location)
    ₹1,700/sqft
  3. 3
    Total cost
    1500 × ₹1,700
    ₹25,50,000
  4. 4
    Cement
    1500 × 0.4 bags/sqft
    600 bags
  5. 5
    Steel
    1500 × 4 kg/sqft
    6000 kg
  6. 6
    Sand
    1500 × 1.816 cft/sqft
    2724 cft
  7. 7
    Aggregate
    1500 × 1.35 cft/sqft
    2025 cft
  8. 8
    Bricks
    1500 × 8 nos/sqft
    12000 nos

Assumptions

  • Thumb-rule (area based) estimate for an RCC framed house; ±10% accuracy.
  • Base rate ₹1,700/sqft for standard quality, location factor 1.
  • Includes structure, masonry, plaster, flooring, doors/windows, electrical, plumbing, painting, waterproofing.
  • Excludes land, approvals, interiors, furniture, compound wall, borewell, water tank.
  • For a detailed BOQ with measurement book, use the plan-based Detailed Estimate.
Need an item-wise BOQ with measurement book, BBS and a drawn plan? Use the Item-wise House BOQ →

House plans close to 1,500 sq ft

Construction cost by built-up area

Frequently asked questions

What is the cost of constructing a 1,500 sq ft house?

About ₹25.5 lakh at standard finish (₹1,700 per sq ft), ₹21.8 lakh basic and ₹36.0 lakh premium, in a tier-2 city, material and labour together. Metros are about 15% higher, small towns about 8% lower.

How many cement bags are needed for 1,500 sq ft?

About 600 bags (0.4 bag per sq ft of built-up area) for the whole house — foundation, frame, brickwork, plaster and flooring.

How much steel is needed for 1,500 sq ft?

About 6,000 kg (6 tonnes) at 4 kg per sq ft for an RCC framed house. The structural drawing and bar bending schedule give the exact figure.

Is 1,500 sq ft the plot size or the built-up area?

These figures are for 1,500 sq ft of built-up area — the total covered floor area of all floors, measured to the outside of the walls. A G+1 house of 750 sq ft per floor is also 1,500 sq ft.

How much is the labour cost for 1,500 sq ft?

Labour is about 30% of the total: roughly ₹7.7 lakh for 1,500 sq ft at standard finish.

Results are preliminary estimates based on standard thumb rules and the inputs given. Final quantities come from drawings and a detailed BOQ. Structural sizes and reinforcement must be checked by a qualified engineer.