Sample house construction agreement with a contractor (fill in the blanks)

A short sample you can print or save as a PDF, then fill in by hand. It covers the ten points that matter most. For the reasons behind each, read the clause guide.

Clause-by-clause guide

House Construction Agreement

1. Parties

This agreement is made on ____ / ____ / ________ at ______________ between Mr/Ms ____________________ (Owner), address ____________________________, PAN ______________, and Mr/Ms ____________________ / M/s ____________________ (Contractor), address ____________________________, PAN ______________.

2. The work

The Contractor will construct a ____ floor house of about ______ sq ft built-up area on Plot / Khasra No. ______ at ______________________, as per the approved plan no. ______ dated ____________ and the structural drawing attached as Annexure A. The scope is: ☐ labour only ☐ material and labour. The following are not included: ____________________________.

3. Price

The Owner will pay ₹ ____________ in total / ₹ ______ per sq ft measured as ______________ / at the item rates in Annexure B. GST is ☐ included ☐ extra at ____ %. Extra work will be done only on a written order that states its rate and effect on time.

4. Payments

Payment will be made by cheque or bank transfer against a receipt, at these stages: advance ____ %; foundation and plinth ____ %; ground floor slab ____ %; first floor slab ____ %; brickwork and plaster ____ %; flooring, doors, plumbing and electrical ____ %; painting and finishing ____ %. The Owner will hold back ____ % as retention until the defect period ends.

5. Material

The Contractor will use only the brands and grades in Annexure C (cement ____________, steel ____________ Fe500D, bricks / blocks ____________, tiles ____________, pipes ____________, wires ____________, paint ____________). The Owner may inspect and reject material, and require tests of steel and concrete cubes at the Contractor's cost.

6. Time and delay

Work starts on ____ / ____ / ________ and will be complete by ____ / ____ / ________. For delay not caused by the Owner, heavy rain or government orders, the Contractor will pay ₹ ________ for every week of delay.

7. Quality and inspection

The work will follow the relevant IS codes and the approved drawings. The Contractor will not pour concrete in the foundation, any column, beam or slab, and will not cover any waterproofing, pipe or conduit, until the Owner's engineer, Mr/Ms ____________, has approved it in writing. Faulty work will be redone at the Contractor's cost.

8. Workers, safety and site

The Contractor is responsible for the wages, safety, insurance and compliance with labour laws for all workers, and for any damage to neighbouring property caused by the work. Water and electricity will be paid by ____________. The Contractor will not sub-contract without the Owner's written permission.

9. Defect period and warranty

For ____ months after handover, the Contractor will fix any defect in the work at his own cost within ____ days of notice. Waterproofing carries a written warranty of ____ years.

10. Ending the agreement and disputes

Either party may end this agreement by ____ days' written notice if the other fails to keep it, and the work done so far will be measured and paid. Any dispute will first be discussed, then referred to ☐ mediation ☐ arbitration at ______________, and the courts of ______________ will have jurisdiction.

Owner signature and date ______________ Contractor signature and date ______________ Witness 1 ______________ Witness 2 ______________

This is a checklist to help owners, not legal advice. Have the final agreement read by a local lawyer, and follow your state's stamp duty and registration rules.