Contractor agreement format for house construction: every clause explained

Twelve groups of clauses that protect a house owner, in plain words. Use it as a checklist when you read the contractor's draft, then fill in the blanks of the sample agreement.

Three common ways to hire

  • Labour-only

    You buy the material. The contractor charges only for labour.

    You can watch the site and want to control brands and cost.

  • Material and labour (turnkey)

    The contractor supplies material and labour for a total or a per sq ft rate.

    You live far away or have little time. Here the brand list in writing is most important.

  • Item-rate

    Every item has an agreed rate and is paid for as it is measured.

    Most transparent. Works best with an item-wise BOQ.

What the agreement must contain

A. Parties and property

  • Full names, addresses, PAN and phone of the owner and the contractor (and the firm's name and registration if any).
  • Plot address, plot or khasra number and area.
  • Date and place of signing.

B. Scope of work

  • The approved plan, number of floors and built-up area.
  • What is included, from excavation to the last coat of paint, or only the structure.
  • What is not included, in plain words: boundary wall, borewell, septic tank, false ceiling, modular kitchen, fittings, the front elevation work.
  • Annexures attached: approved plan, structural drawing, BOQ or rate sheet and the material specification list.

C. Price and rates

  • Total amount, per sq ft rate or item-wise rates.
  • How the area is measured for a per sq ft rate (built-up or carpet, whether balcony and parking are counted).
  • GST: included or extra, and at what rate.
  • Rates for extra work agreed in advance, such as extra depth of excavation or rock.
  • Whether the rate is fixed or can change if steel and cement prices rise, and by what formula.

D. Payment schedule

  • Link every payment to a stage of the work, not to a date.
  • Pay by cheque or bank transfer and take a written receipt each time. Never pay in cash without a receipt.
  • Never pay for work ahead of the stage reached.
  • Hold back a retention until the defect period ends.

E. Material

  • A written list of brand and grade: cement (OPC 53 or PPC), steel (Fe500D and make), bricks or AAC blocks, sand, tiles, pipes, wires, paint.
  • Watch the words "or equivalent". They are the usual door for swapping a brand.
  • Your right to see and approve samples, and to reject poor material.
  • Material tests (steel, concrete cubes) and who pays for them.

F. Time

  • Start date, completion date and milestone dates.
  • A penalty for delay, as a fixed amount or a percent per week.
  • Which delays are excused: heavy rain, late payment or drawings from the owner, government orders.

G. Quality and inspection

  • The work follows the relevant IS codes and the approved drawings.
  • Hold points where work cannot go on without your engineer's written approval: foundation steel, every slab and beam steel before pouring, waterproofing, and pipes and conduits before covering.
  • Name of the site engineer or supervisor, and a daily progress register.
  • Faulty work is broken and redone at the contractor's cost.

H. Changes and extra work

  • Every change in writing, with its rate and effect on time, signed by both before the work starts.
  • No verbal "do it now, we will settle later".

I. Site, workers and safety

  • The contractor is responsible for workers' wages, accidents, insurance and labour laws.
  • Safety on site: scaffolding, nets, helmets.
  • Who pays for water and electricity, and who clears the debris.
  • Damage to the neighbour's wall or property is the contractor's cost.
  • No sub-contracting without your written permission.

J. Defect period and warranty

  • A defect liability period of about 12 months after completion, in which visible defects (cracks, seepage, lifting tiles) are fixed at the contractor's cost.
  • A separate written warranty for waterproofing, with the number of years.

K. Ending the agreement

  • When each side can end it: work stopped, poor quality, payment not made.
  • The notice period, and how the work done so far is measured and paid.
  • Your right to appoint another contractor to finish.

L. Disputes

  • First talks, then mediation or arbitration, and the city whose courts have jurisdiction.

M. Handover and signing

  • The method of handover: snag list, final measurement, final bill, drawings and warranties.
  • Stamp paper as your state requires, two witnesses, and both parties' signature or initial on every page.

Example: stage-wise payment plan

This is only an example for a G+1 house. Agree your own percentages with your engineer.

Example stage-wise payment plan
Stage reachedPayment
On signing the agreement (advance)10%
Foundation and plinth complete15%
Ground floor slab cast20%
First floor slab cast20%
Brickwork and plaster complete15%
Flooring, doors, windows, plumbing and electrical10%
Painting and finishing5%
Retention, after the defect period5%
Total100%

Red flags

  • "Everything is included" with no written scope.
  • "Good company material" instead of a named brand.
  • Pressure to start work without a written agreement.
  • A large advance, or "pay first, drawings later".
  • Asking for cash only, with no receipt.
  • No rates fixed for extra work.
  • No delay penalty and no retention.
Open the sample agreement with blanks →

This is a checklist to help owners, not legal advice. Have the final agreement read by a local lawyer, and follow your state's stamp duty and registration rules.

All 14 stages

Frequently asked questions

Is a written contractor agreement necessary for building a house?

Yes. A written agreement that lists the scope, the rate, the payment stages, the brands, the time and the penalty is the single best protection an owner has. A verbal promise cannot be proved if there is a dispute.

How should payments to a house contractor be made?

Link payments to stages of work such as foundation, each slab and plaster, and pay by cheque or bank transfer with a receipt. Keep about 5 percent as retention until the defect period ends. Never pay far ahead of the work done.

Do I need stamp paper for a contractor agreement?

The stamp duty on such agreements depends on the state and the amount, so ask a local lawyer or the sub-registrar office. Having it printed on the right stamp paper and signed before witnesses makes it much easier to rely on.