Site preparation and marking before construction starts
Stage 6 of 14 · About 1 to 2 weeks
Most costly mistakes are made in the first week: a wall a foot over the setback, a plinth lower than the road. Both are decided here, on the ground, before any concrete is poured.
Do not let digging start until you have seen and photographed the marking.
What you need to know
Clear the plot of bushes, roots and rubbish, level it roughly, and put up a gate and fence. Security and a clean site save material from theft and waste.
Marking (setting out) must follow the approved map: plot boundary, front, rear and side setbacks, then the column centre lines. Use a tape and the 3-4-5 triangle for right angles, and mark with pegs and lime or string.
Fix a permanent benchmark (a reference level) on a fixed object, such as a boundary wall or a pillar, and write down its level against the road. Plinth height is measured from it. A plinth that ends up below the road level lets rain water into the house.
Arrange a temporary water and electricity supply, and decide in the agreement who pays. Make a dry shed for cement and keep steel on blocks under cover. Sand and aggregate need separate, clean heaps.
Check this before you move on
- Marking matches the approved map, with setbacks measured and written down
- Diagonals of the plot and of the house rectangle are equal (square corners)
- Benchmark fixed and its level against the road is recorded
- You signed or photographed the marking before digging started
- Cement shed is dry, raised off the ground, and bags are stacked and used in order
- Water and power arrangement and who pays are in writing
Common mistakes
- Marking by the mason's eye, without a tape or a diagonal check
- No benchmark, so the plinth level is argued about later
- Building up to the neighbour's line instead of the approved setback
- Storing cement bags on bare ground or in the open
Watch how it is done
Search YouTube for site videos of this stage in Hindi: Open YouTube search
Tools for this stage
Make my item-wise BOQAll 14 stages
Frequently asked questions
How high should the plinth be above the road?
Many local bye-laws ask for a plinth at least about 450 mm (1.5 ft) above the road or ground level, and more where water collects. The rule differs by city, so check your approved map and ask your engineer.
Is bhumi pujan needed before construction?
It is a family and community custom, not a technical or legal step. Do it if it matters to you, but do not let it replace the marking check and the benchmark.
Results are preliminary estimates based on standard thumb rules and the inputs given. Final quantities come from drawings and a detailed BOQ. Structural sizes and reinforcement must be checked by a qualified engineer.