House foundation: steps, depth and what to check before concrete
Stage 7 of 14 · About 3 to 5 weeks
The foundation is the one part you can never inspect again once it is covered. Everything above it depends on what happened in these few weeks, so this is the stage to be on site.
Be on site, or have your engineer there, to see the footing steel before the concrete is poured.
What you need to know
The type and depth of the foundation come from the soil test and the structural drawing, never from the mason's habit. Isolated footings under each column are common for G+1 and G+2 houses on good soil. Weak or filled soil may need a raft or piles.
Dig to the drawn size and depth. The bottom must be firm, level and free of loose soil and standing water. In this site's sample estimate the column footings are dug 1.5 m deep in ordinary soil. Your own depth must follow your soil test.
A 100 mm layer of plain cement concrete (PCC, usually 1:4:8) goes first as a clean, level base. The footing steel then sits on cover blocks so that it has about 50 mm of concrete below it.
The column starter bars must be in the exact position and height shown on the drawing, with the lap length left for the column above. Then come the plinth beam, anti-termite treatment, backfilling in layers and the plinth filling.
Concrete must be tested. For each day of casting, make a set of 3 cubes, cure them and test them at 28 days. Keep the results with your papers.
Check this before you move on
- Soil test report is with the engineer and the foundation drawing follows it
- Excavation size and depth match the drawing; bottom is firm, level and dry
- PCC bed is laid, 100 mm thick, before any steel goes in
- Footing steel: bar diameter, count, spacing and 50 mm cover blocks match the drawing
- Steel is free from loose rust, oil and mud
- Column starters are in the right place, height and lap length
- Concrete is mixed by measure, not by guess; water is not added on the pour
- Cube samples taken and marked with date and location
- Anti-termite treatment done before backfilling and plinth filling
- Curing for at least 7 days with ordinary cement, 10 days or more with PPC or in hot weather
Common mistakes
- Digging less deep than drawn to save time and labour
- Skipping the PCC bed, so the steel rests on soil
- No cover blocks, so the steel touches the soil and rusts
- Pouring concrete into standing water or loose soil
- No curing, or curing only for a day or two
- Column starters cast off-centre and bent into place later
How much of the budget this stage takes
In this site's sample G+1 house (30×40 ft plot, standard finish) the items for this stage are about 8% of the construction cost: Earthwork and foundation. Your own share will differ with design and rates.
Watch how it is done
Search YouTube for site videos of this stage in Hindi: Open YouTube search
Tools for this stage
Make my item-wise BOQAll 14 stages
Frequently asked questions
How deep should the foundation of a G+1 house be?
It depends on the soil, so there is no single number. For ordinary soil under two-storey houses, isolated footings are often founded somewhere around 1.2 to 2 m below ground, but your soil test and structural drawing must decide it. Never go shallower than the drawing.
Is a soil test really needed for a small house?
Yes. The test costs very little compared with the foundation, and it tells the engineer how much load the soil can carry. A wrong guess here shows up later as cracks that are very costly to fix.
Results are preliminary estimates based on standard thumb rules and the inputs given. Final quantities come from drawings and a detailed BOQ. Structural sizes and reinforcement must be checked by a qualified engineer.