House painting and finishing: putty, primer, paint and fittings
Stage 13 of 14 · About 3 to 5 weeks
Paint is the last layer and the first thing every visitor sees. It is also the stage where shortcuts are easiest to hide, such as a missing coat or a thinned-down paint.
See the paint tins opened and the coats counted, before the painter's bill is paid.
What you need to know
Let the plaster dry well before putty and paint, usually a few weeks. Painting damp walls leads to peeling, patches and white salt marks. Fix any hairline cracks and leaks first.
A usual internal system is two coats of wall putty, sanding between coats, one coat of primer, and two coats of emulsion. For the outside, use a weather-proof exterior paint on a suitable primer.
Insist on sealed tins of the agreed brand and shade, opened in front of you. Thinning paint with extra water is the commonest way to cheat. Note the batch number so that a repair later matches.
Do the wood work, false ceiling and tiling work before painting, and fix switches, fans, lights and sanitary fittings after painting, so that nothing gets splashed. Do a final cleaning once all this is done.
Check this before you move on
- Walls are dry; cracks and leaks are fixed before putty
- Two coats of putty, sanded, with a smooth finish under a bright torch light
- Primer applied before the paint
- Paint tins are sealed, of the agreed brand and shade, and opened on site
- The number of coats matches the agreement
- No roller marks, drips or patches in daylight and at night
- Fittings are fixed, tested and cleaned; spare paint is handed over
Common mistakes
- Painting over damp or dusty plaster
- Skipping the primer or the second coat
- Thinning paint with water to make it last longer
- Fixing switch plates and fittings before painting, then painting around them
How much of the budget this stage takes
In this site's sample G+1 house (30×40 ft plot, standard finish) the items for this stage are about 11% of the construction cost: Electrical and painting. Your own share will differ with design and rates.
Watch how it is done
Search YouTube for site videos of this stage in Hindi: Open YouTube search
Tools for this stage
Make my item-wise BOQAll 14 stages
Frequently asked questions
How long to wait before painting new plaster?
A common rule of thumb is to let it dry for a few weeks, about 3 to 4, and longer in monsoon or on thick plaster. The wall must be dry to the touch and show no damp patch. Painting too early causes peeling and salt marks.
Results are preliminary estimates based on standard thumb rules and the inputs given. Final quantities come from drawings and a detailed BOQ. Structural sizes and reinforcement must be checked by a qualified engineer.