Electrical and plumbing work: what to check before the walls are plastered
Stage 11 of 14 · About 2 to 4 weeks, along with brickwork and plaster
Once the plaster is on, every wire and pipe is hidden for good. Changing a point later means breaking a finished wall. This stage is about planning and checking while everything is still open.
Do not allow plastering until the wiring and pipes are inspected, tested and photographed.
What you need to know
Mark every light, fan, switch, socket, AC and geyser point on a wall-by-wall drawing with the owner, before any chase is cut. Think about where furniture, the bed head, the TV and the kitchen appliances will go.
Use ISI-marked copper wire in PVC conduit. In common Indian practice 1.5 sq mm wire serves lights and fans, 2.5 sq mm serves sockets, and 4 sq mm serves an AC or geyser. Separate circuits with MCBs, an RCCB or ELCB for safety, and proper earthing, are essential.
Use ISI-marked pipes for water supply and drainage. Waste lines need a continuous slope, commonly between about 1 in 40 and 1 in 60, with no sags. Fix traps, floor drains and the vent line as the plumber's drawing shows.
Pressure-test the water pipes before they are covered, and keep them under pressure for 24 hours. A drop in pressure means a leak somewhere in the wall.
Photograph every wall and floor with the pipes and conduits visible and a tape showing the distance from a corner. These photos will tell you where it is safe to drill for the next twenty years.
Plan the septic tank or sewer connection, the soak pit, the sump and the overhead tank, and the borewell if needed, along with the outside drainage level.
Check this before you move on
- Point drawing agreed and signed for each room before chasing
- Wire size and make as agreed; circuits separated, with MCB and RCCB
- Earthing pit made and tested
- Conduits are fixed firmly, with no loose joints or sharp bends
- Pipes are ISI-marked; slope on waste lines is continuous
- Water lines pressure-tested for 24 hours with no drop
- Bathroom floor drains and traps are fixed at the right level
- Dated photos of every wall with pipes and conduits are saved
Common mistakes
- Deciding the point positions after the chasing is done
- Thin, non-ISI wire that heats and wastes power
- No earthing, or an earth wire that is not connected to anything
- Burying pipes without a pressure test
- Waste pipes laid flat, so they block again and again
How much of the budget this stage takes
In this site's sample G+1 house (30×40 ft plot, standard finish) the items for this stage are about 6% of the construction cost: Plumbing and sanitary. Your own share will differ with design and rates.
Watch how it is done
Search YouTube for site videos of this stage in Hindi: Open YouTube search
Tools for this stage
Make my item-wise BOQAll 14 stages
Frequently asked questions
What wire size is used for lights, sockets and AC in a house?
In common Indian practice, 1.5 sq mm copper wire is used for lights and fans, 2.5 sq mm for power sockets and 4 sq mm for an AC or geyser, each on a separate circuit with the right MCB. Your electrician or engineer must confirm it for your loads.
Results are preliminary estimates based on standard thumb rules and the inputs given. Final quantities come from drawings and a detailed BOQ. Structural sizes and reinforcement must be checked by a qualified engineer.