Plaster, flooring, tiles, doors and windows: a checklist for owners
Stage 12 of 14 · About 4 to 8 weeks
This is where the house starts to look finished, and where the biggest bills for finishing begin. Quality shows in small things: a straight wall, a floor with no hollow tiles, a door that closes without a push.
Witness the bathroom flood test before any tile is laid.
What you need to know
Plaster is usually about 12 mm inside and 15 to 20 mm outside, in cement mortar such as 1:4 or 1:6 as agreed. Check the surface with a straight edge, and cure it with water for about 7 days so it does not crack.
Floors need a level base and a slope towards the drain in bathrooms, kitchens and the wash area, commonly about 1 in 100. Lay tiles on a proper bed or adhesive with full contact, and tap each tile to check that it is not hollow.
Waterproof every bathroom floor and the lower part of its walls before tiling, then flood it and hold the water for 24 to 48 hours. Check the ceiling below. Do this test before the tiles go on.
Door and window frames must be plumb, square and fixed firmly with the right clearance. Decide the frame material (wood, steel, UPVC or aluminium), the shutter type and the hardware early, because the lead time can be weeks.
Order tiles and fittings in one go, with about 5 to 10 percent extra, from the same batch so that the shade matches. Keep the leftover tiles for repairs.
Check this before you move on
- Plaster is straight and plumb, with no hollow sound and no hairline cracks
- Plaster is cured for about 7 days
- Floor level is even and slopes to the drains in wet areas
- Bathroom waterproofing done and flood-tested for 24 to 48 hours
- Tiles are laid with full contact (tap test), straight joints and even spacing
- Frames are plumb and square; shutters open and close freely
- Brand, size and batch of tiles match your order; spare tiles are kept
Common mistakes
- Plastering over a wall that was never properly cured or is full of dust
- Tiles placed on dabs of mortar, leaving hollow spots that crack later
- Fixing bathroom tiles before testing the waterproofing
- Floors with no slope, so water stands in the bathroom
- Ordering tiles in batches from different lots
How much of the budget this stage takes
In this site's sample G+1 house (30×40 ft plot, standard finish) the items for this stage are about 28% of the construction cost: Plastering, Flooring, tiles and waterproofing, Doors, windows, ventilators. Your own share will differ with design and rates.
Watch how it is done
Search YouTube for site videos of this stage in Hindi: Open YouTube search
Tools for this stage
Make my item-wise BOQAll 14 stages
Frequently asked questions
How thick should wall plaster be?
Usually about 12 mm for internal walls and 15 to 20 mm for external walls. Plaster much thicker than this tends to crack and costs more material. If the wall is very uneven, fix it with a coat in two layers, not one thick layer.
Results are preliminary estimates based on standard thumb rules and the inputs given. Final quantities come from drawings and a detailed BOQ. Structural sizes and reinforcement must be checked by a qualified engineer.