RCC columns, beams and slab: steel, cover, pouring and curing
Stage 8 of 14 · About 4 to 6 weeks per floor
The frame carries the whole house. Steel, concrete and shuttering decide how long it stands, and each pour is a one-time event: once the concrete is in, you cannot see the steel again.
Never let a slab or beam pour start until you or your engineer have checked the steel and signed it off. Take photos of every bar layout.
What you need to know
Sizes and steel come only from the structural drawing. For reference, the sample G+1 house in this site's BOQ uses 300 × 300 mm columns, 230 × 400 mm beams, a 125 mm slab, M20 concrete and Fe500D steel. Yours may differ.
The order is: column steel, column shuttering, column pour, then beam and slab shuttering, beam and slab steel, electrical conduits and sleeves, inspection, and finally the beams and slab poured together in one go.
Use Fe500D TMT bars of a reputed make with the ISI mark. Bars must be straight, with only a light film of rust and no oil or mud. Lap lengths, stirrup spacing and bends must be exactly as drawn. Stirrups are closer together near beam-column joints.
Cover is the concrete between the steel and the surface. It protects the steel from rust and fire. As drawn, it is typically about 40 mm for columns, 25 to 30 mm for beams, 20 to 25 mm for slabs and 50 mm for footings. Use cover blocks, not stones or broken bricks.
Concrete must be M20 or better as drawn, mixed by weight batching or bought as ready-mix. Do not add water on site to make it flow. Compact it with a vibrator so that no honeycombs are left. Pour the slab continuously without a cold joint.
Do not remove shuttering early and keep the props where the engineer says. Cure the slab by ponding water for at least 7 days (10 days or more with PPC or in hot weather).
Check this before you move on
- Bar diameter, number of bars, spacing and bends match the drawing (count them)
- Lap lengths and stirrup spacing are as drawn, closer near joints
- Cover blocks are in place under and beside the steel
- Shuttering is tight, level, plumb and well propped; no gaps for the cement to leak
- Conduits, sleeves for pipes and cut-outs are fixed before the pour
- Slab thickness is marked with pegs and checked while pouring
- A slump test is done, and cube sets are taken for every day of casting
- Concrete is vibrated, and the slab is poured in one go
- No pouring in heavy rain; fresh concrete is covered if it rains
- Curing starts the next day and goes on for the full period
Common mistakes
- Swapping a thicker bar for a thinner one (for example 12 mm for 16 mm) to save steel
- Cutting or bending beam steel to let a pipe through
- Forgetting sleeves and drilling through the beam later
- Adding water to the mix because it is easier to place
- Honeycombs patched with plaster instead of being reported to the engineer
- Removing props and shuttering early to reuse them
How much of the budget this stage takes
In this site's sample G+1 house (30×40 ft plot, standard finish) the items for this stage are about 34% of the construction cost: RCC structure – M20 / Fe500D, Staircase (dog-legged RCC). Your own share will differ with design and rates.
Watch how it is done
Search YouTube for site videos of this stage in Hindi: Open YouTube search
Tools for this stage
Make my item-wise BOQAll 14 stages
Frequently asked questions
How many days before slab shuttering can be removed?
Side shuttering of columns and beams can usually come off in a day or two, but the slab props must stay much longer, often 7 to 14 days depending on the span. See the full table on our shuttering removal page and follow your engineer.
Ready-mix concrete or site mix?
Ready-mix gives a more consistent grade if it is ordered for the right strength and delivered on time. Site mix works if materials are measured by weight and water is controlled. Either way, take cubes and test them.
Results are preliminary estimates based on standard thumb rules and the inputs given. Final quantities come from drawings and a detailed BOQ. Structural sizes and reinforcement must be checked by a qualified engineer.